JammuHanging for decades, Execution today

Hanging for decades, Execution today

Date:

Sinha marks work completion on 35 power projects to ease power cuts

Augmentation of 367 MVA capacity in

Jammu Tawi, July 15: Giving a major push to strengthen the Power sector in J&K, Lieutenant Governor, Manoj Sinha Thursday inaugurated 35 power projects worth Rs 44.14 crores, augmenting the overall capacity in Jammu Division by 367 MVA.

On the occasion, the Lt Governor also launched several e-Services of Power Development Department, including the new provision for submitting an application for getting a new electricity connection through online mode. Further, people can avail themselves facilities of online bill payment, online complaint redressal, online security deposit calculation, besides using the online customer portal for their convenience.

“Decade long overdue up-gradation of power infrastructure is being done in a sustained manner. We are eliminating the legacy of delays. Languishing projects hanging for long are being completed in record times”, he added.

I want to assure all the citizens of Jammu and that the administration is continuously working towards your needs and a long-term strategy is being implemented on the ground to ensure 20-22 hours of continuous electricity like other parts of the country.

The capacity augmentation of the Barn Grid station which is being inaugurated today should have been done in 2012 itself because in the same year it was targeted that the capacity of this grid station would be increased to 480 MVA by installing an additional capacity of 160 MVA. Now, this important power project has been completed in the record 119 days despite the Covid pandemic which has been hanging for 9 years. This project will immensely benefit the remote areas of Poonch, Rajouri, Akhnoor, Jourian, Reasi and the adjoining areas of Jammu, the Lt Governor asserted.

These are the reforms the UT Government has brought in the work in J&K. I would like to congratulate all the officers and engineers of the Power Department for this, he added.

There is another example of Sawalakot project which was planned to be built in 1984. It was expected that 1856 MW of electricity would be generated from this project, but that too remained like a dream. This project was hanging for 36 years, which has been given the green signal this year, the Lt Governor observed.

Terming augmentation of the power grid stations imperative to meet the increasing power demand, the Lt Governor stated that the Gladini Grid station whose capacity has been upgraded today has been long awaiting its capacity augmentation. Draba-Chandak transmission line which was hanging since 2014 was also completed to further strengthen the power distribution system.

Moving away from the old system, we have executed 35 power projects today, which also include many transmission and distribution projects, thus strengthening the system and management capacity of the entire Jammu division, added the Lt Governor.

In Jammu, the preparation was well made in advance for the summers, but unfortunately, the general public had to suffer a lot, he said. I assure you that the power distribution system of Jammu division will be strengthened to its full potential so that in future, the people do not have to face any inconvenience.

Clear-cut instructions have already been passed to the power department to work on a war footing in ensuring the uninterrupted power supply, besides several meetings, were held with experts in the month of March-April in Jammu to improve the power supply system using the latest technologies. Despite all these efforts, many reasons have been identified for the problems present in the present system, and they are also being resolved, he observed.

Mentioning the deliberations made during the recent review meeting of the Power Department, the Lt Governor observed that a provision has been suggested for incentivizing the field staff for their good work, besides taking strict action against those who are negligent.

Another key issue that came to the fore in the meeting was to arrange for real-time monitoring in towns where electricity consumption is high so that people do not have to face problems due to undeclared cuts. And, instructions were issued to the Principal Secretary, Power Department and his team to work on this direction said the Lt Governor.

There is no shortage of hydro resources in Jammu and Kashmir. We have a generation capacity of 14,867 MW of electricity, but in the last 70 years we were able to generate only 3504 MW. With our determined efforts, we will be able to generate additional power of 3498 MW in the next 4-5 years. With the rapid pace of development, where it took us 70 years to reach, we will reach there in just 5 years, maintained the Lt Governor.

Arun Kumar Mehta, Chief Secretary, speaking on the occasion complimented the department on the completion of the new projects. He called upon the officers to move towards digital platforms for efficient service delivery, besides making objective efforts to achieve better demand side management.

Rohit Kansal, Principal Secretary, Power Development Department gave a detailed briefing about the newly inaugurated power projects and new e-services of the Power department. He outlined broad reforms and steps being undertaken by the department to upgrade the power infrastructure in the region

Dr RP Singh, Chairman JKPCL; Jagmohan Sharma, Chairman JPDCL; Anand Mohan, Chairman KPDCL, Dr N S Saxena Chairman JKPTCL; Nasib Singh, MD JKPTCL; Gurmeet Singh, MD JPDCL; Chief Engineers and other senior officials of the power department were also present on the occasion.

The projects inaugurated today included- Augmentation of 220/132/33 KV Grid Station Barn from 2×160 MVA to 3×160 MVA, Augmentation of 132/33 KV Grid Station Canal from 100 MVA (2X50) MVA to 120 MVA (2X50+1×20) MVA, Augmentation of Grid Station Udhampur at 132/33 KV Level from 70 MVA (20+50) MVA to 100 MVA (2×50) MVA, Augmentation of Grid Station Gladni at 132/33 KV Level from 150 MVA (3×50) MVA to 170 MVA (3×50+1X20) MVA, Augmentation of 132/33 KV, GSS, Sidhra-ll from 70 MVA (1×50+1×20) MVA to 100 MVA (2×50) MVA, Augmentation of 33/11 KV R/S from 3.15 MVA to 6.3 MVA at Pallanwalla, Additional 6.3 MVA Transformer at 33/11 KV R/S Gadi Garh, Additional 3.15 MVA Transformer at 33/11 KV R/S Rangpur Moulana, Additional 6.3 MVA Transformer at 33/11 KV R/S Dansal, Augmentation of 33/11 KV R/S from 3.15 MVA to 6.3 MVA at Kaleeth, New 1×6.3 MVA 33/11 KV Sub Station Shahzadpur and Additional 6.3 MVA Transformer at 33/11 KV R/S Jhajjar Kotli.

Northlines
Northlines
The Northlines is an independent source on the Web for news, facts and figures relating to Jammu, Kashmir and Ladakh and its neighbourhood.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Share post:

Popular

More like this
Related

Building, Car Of Alleged Drug Peddler Attached In J&K’s Rajouri

JAMMU, May 4: A multi-storey business establishment and a...

NC’s Farooq Abdullah Calls For Meaningful Solution To Issues Of Kashmiri Pandit Migrants

JAMMU, May 4: National Conference (NC) president Farooq Abdullah...

Shaken By Surgical Strikes, Pak Leaders Now Praying Cong ‘Shehzada’ Becomes India’s PM

Palamu (Jharkhand), May 4: Prime Minister Narendra Modi on...