Home Jammu Chief Secretary reviews PMGSY progress in J&K

    Chief Secretary reviews PMGSY progress in J&K

    PMGSY-IV to construct 646 new roads across J&K at an investment of ₹7,790 Cr

    Srinagar, Jul 14: Chief Secretary, Atal Dulloo today chaired a review meeting to assess the progress of works being executed under the Pradhan Mantri Gram Sadak Yojana (PMGSY) across the Union Territory.

    During the review, the Chief Secretary took a comprehensive stock of the physical and financial progress achieved under PMGSY Phases I, II and III, besides examining the implementation strategy and future roadmap for PMGSY-IV, which is the largest rural connectivity programme undertaken in Jammu & Kashmir so far.

    While reviewing the implementation of PMGSY-IV, the Chief Secretary described the scale of investment envisaged under the programme as phenomenal, observing that it reflects the Government’s unwavering commitment towards strengthening rural infrastructure and ensuring equitable development across Jammu & Kashmir.

    He said the unprecedented investment in rural road connectivity would not only provide all-weather access to far-flung habitations but also serve as a catalyst for socio-economic transformation by improving access to education, healthcare, markets, tourism and employment opportunities.

    Expressing satisfaction over the substantial progress achieved under the PMGSY, the Chief Secretary, however, stressed that the handful of projects still pending under the earlier phases must be completed without any further delay. He directed the Public Works (R&B) Department to fix responsibility for inordinate delays wherever warranted and ensure greater accountability in project execution.

    The Chief Secretary further impressed upon the Department to adopt a coordinated approach with the Divisional Commissioners, Deputy Commissioners and the Forest Department for expeditious resolution of all pending bottlenecks, particularly those relating to forest clearances, land-related issues, utility shifting and other statutory approvals that have impeded the timely completion of certain projects.

    Emphasising the need for close field-level monitoring, the Chief Secretary directed all Deputy Commissioners to personally review the progress of PMGSY projects in their respective districts at regular intervals and facilitate inter-departmental coordination to remove obstacles hindering execution.

    He instructed that every effort should be made to ensure completion of all balance works well before the stipulated sunset dates of the respective PMGSY phases, while simultaneously maintaining the momentum of implementation under PMGSY-IV so that the pace of progress remains steady, timely and outcome-oriented.

    Speaking on the occasion, Additional Chief Secretary, Public Works (R&B) Department, Anil Kumar Singh, reiterated the Department’s firm commitment towards the timely completion of all pending works sanctioned under the earlier phases of PMGSY. He made out that the focused efforts are underway to fast-track forest and statutory clearances, expedite the tendering and award of newly sanctioned works, and ensure early commencement of projects on the ground.

    Reviewing PMGSY-IV, the Chief Secretary noted that the programme marks a major expansion of rural road infrastructure in the Union Territory. Under the first two batches of PMGSY-IV, 646 roads with a total sanctioned length of 3,381 kilometres and an estimated cost of ₹7,790 Cr have been approved for connecting 792 habitations.

    The meeting concluded with a reaffirmation of the Government’s resolve to strengthen rural infrastructure and accelerate socio-economic development through enhanced connectivity in every corner of Jammu & Kashmir.