Jammu Tawi, September 15-In order to carry out the construction work under R-APDRP scheme, the power supply to Toph, Udheywala, Om Nagar, Talab Tillo, Manorma Vihar, Lower Roop Nagar, Muthi PHE, Bantalab, Janipur, Lakkar Mandi and its adjoining areas fed from T-2, T-3, T-4, T-5, MU-4, UD-3, J-2, J-3, J-6, MU-2, MU-5, MU-7, MU-9, RN-1, RN-3, BT-1, BT-3, BT-4, RN-4, UD-1, UD-2, SN-1, SN-3 and SN-4 feeders shall remain affected from September 15 to 30 (on alternate days) from 6 am to 10 am.
Meanwhile, to carry out the development works by M/s IRCON International Ltd under R-APDRP scheme, the shutdown of 11 KV CH-3 and CH-5 feeder is being observed.
During the shutdown, the power supply to Channi Himmat and its adjoining areas shall remain affected on September 16 and 17 from 7 am to 11 am.
Likewise, to carry out works by M/s IRCON International Ltd under R-APDRP scheme, the shutdown of 33 KV G-2 feeder is being observed.
During the shutdown, the power supply to Gandhi Nagar, Bahu Plaza, Divisional Commissioner Office, NHPC Guest House, Architect Building, RBI, Narwal areas etc shall remain affected onSeptember 18 and 25 from 7 am to 12 noon.