JammuMehar Tunnel excavation put on hold due to sidewall deformations

Mehar Tunnel excavation put on hold due to sidewall deformations

Date:

Tawi, Dec 18:  The excavation work for the Mehar tunnel along the 270-km Jammu-Srinagar highway has been suspended due to the development of “pressure and bulges” on its sidewalls, officials said on Monday.

The construction of the 780-metre C-type tunnel started over one-and-a-half years ago to bypass the slide-prone Mehar-Cafeteria stretch in Jammu and 's Ramban district.

The excavation work on the Cafeteria Morh side of the tunnel was suspended in June this year after its mouth was damaged by a massive landslide. Nearly 400 metres of excavation work has been completed so far.

An official of DMR Construction, which is carrying out the construction work, said for the safety of the workers, the excavation work was suspended after “pressure and bulges” were noticed on the side walls.

“All machinery and manpower were withdrawn from the tunnel project on December 12. The company has informed the National Highways Authority of (NHAI) and joint teams of experts and designers are likely to visit the tunnel for a thorough investigation,” a senior official of DMR Construction Vinay Kumar said.

The work on the four-laning of the Jammu-Srinagar national highway started in 2011 and has already missed several deadlines due to the sluggish pace of work.

 

Northlines
Northlines
The Northlines is an independent source on the Web for news, facts and figures relating to Jammu, Kashmir and Ladakh and its neighbourhood.

Share post:

Popular

More like this
Related

PM Promises Justice for Recent Terror Attacks During Public Address.

SRINAGAR, June 20: Prime Minister Narendra Modi on Thursday...

From royalty to legacy: Karan Singh’s 75-year public journey!

JAMMU, Jun 20: Veteran Congress leader and former governor...

PM’s 2-day Srinagar visit kicks off with Yoga Day event!

Srinagar, June 20: Prime Minister Narendra Modi on Thursday...